Thursday 27 February 2014

Formwork done

Earlier than expected, we have our piers, plumbing and form work done! Wonder how soon we will have a slab. Certainly have something to look forward to when we head up on Saturday!


Just a bit of an edit - got to have a look in person on Saturday which was great! Although due to the massive amount of rain on Friday we have a moat, lap pool and mud bath!
This is the view looking at the alfresco area down to the road.

With any luck we have a bit of dry weather this week and can get a slab poured.


And this one looking toward the garage with our 8 course step down and drop edge beam.


Tuesday 25 February 2014

All systems go!

Super exciting day today - we have commenced site works!
Felt like today was never going to come. We were lucky to get some happy snaps from our neighbour who is building 4 doors down. Im still waiting on Allworth to let me know they have started..

Anyway, here are a few pics. Heading up on Saturday and cant wait to see it in person!




Wednesday 12 February 2014

So So Close!

We are so close now to getting this house build started!
Received final kitchen and construction plans today, and Letter of Commencement was sent off last week. This means their 20 days to start building brings us to March 4th at the latest to commence - lets hope sooner!!